A project has tasks A, B, C, and D along its critical path with expected times of 13, 6, 17, and 23 days, respectively. Task C depends only on completion of task B for its final week but otherwise independent. If fast tracking is applied, the expected time of project completion, in days, and the probability of completion in 59 days, respectively are (assume that with or without fast tracking, standard deviation in the expected time of completion is 5 days):
A. 49, 97.72% B. 43, 99.93%
C. 53, 88.49% D. 59, 50.00%

Answers

Answer 1

The correct option for the given question is option (B) 43, 99.93%. Fast tracking implies that the critical path must be shortened or shortened, even if it raises the risk of failure of other tasks. Expected Time (ET) is equal to the sum of Optimistic Time (a), Most Likely Time (m), and Pessimistic Time (b), all of which are divided by 3.

The correct option for the given question is option (B) 43, 99.93%.

Explanation: Fast tracking implies that the critical path must be shortened or shortened, even if it raises the risk of failure of other tasks. Expected Time (ET) is equal to the sum of Optimistic Time (a), Most Likely Time (m), and Pessimistic Time (b), all of which are divided by 3.

E (Expected Time) = (a + 4m + b)/6.

Variance is determined by determining the difference between the optimistic and pessimistic times and then dividing it by 6 squared.

Variance = (b-a)^2/36,

whereas Standard Deviation = sqrt(variance).

Fast tracking might help to shorten the duration of a project, but it also increases the risk of project failure and rework. Furthermore, the critical path might be more challenging to manage since any delay in the critical path tasks might significantly delay the project's completion.

Task C depends only on completion of task B for its final week but otherwise independent. If fast tracking is applied, the expected time of project completion, in days, and the probability of completion in 59 days, respectively are (assume that with or without fast tracking, standard deviation in the expected time of completion is 5 days).

Task A: 13 days

Task B: 6 days

Task C: 17 days

Task D: 23 days

Total Duration = 13+6+17+23 = 59 days

Expected Time: ET = (a + 4m + b)/6

Time of A = 13 (optimistic) + 22 (4 times most likely) + 23 (pessimistic)/6 = 19 days

Time of B = 6 (optimistic) + 8 (4 times most likely) + 10 (pessimistic)/6 = 8 days

Time of C = 17 (optimistic) + 28 (4 times most likely) + 29 (pessimistic)/6 = 24 days

Time of D = 23 (optimistic) + 42 (4 times most likely) + 44 (pessimistic)/6 = 34 days

Total Duration = 19 + 8 + 24 + 34 = 85 days

The variance of Task A is 36 - 0 = 36.

The variance of Task B is 10 - 0 = 10.

The variance of Task C is 144 - 0 = 144.

The variance of Task D is 121 - 0 = 121.

The project's total variance is 311.

Probability of project completion in 59 days: Z = (X-μ)/σX = 59

μ = 85

σ = 5P

(X ≤ 59) = P (Z ≤ (59 - 85)/5) = P (Z ≤ -5.2) = 0.000032

By using this equation, we will get: Z = (X-μ)/σX = 43

μ = 85-18

σ = 5P

(X ≤ 43) = P (Z ≤ (43-85+18)/5) = P (Z ≤ -3.4) = 0.000335

It has been shown that the expected time of project completion, in days, and the probability of completion in 59 days, respectively are (assume that with or without fast tracking, standard deviation in the expected time of completion is 5 days) 43 and 99.93%.

To know more about Probability visit: https://brainly.com/question/32117953

#SPJ11


Related Questions

What is the length of SR 9?.

Answers

The length of SR will be 15 units, using Pythagoras' theorem

What is Pythagoras' theorem?

The hypotenuse's square is equal to the sum of the squares of the other two sides if a triangle has a straight angle (90 degrees), according to the Pythagoras theorem. Remember that BC2 = AB2 + AC2 in the triangle ABC signifies this. Base AB, height AC, and hypotenuse BC are all used in this equation. The longest side of a right-angled triangle is its hypotenuse, it should be emphasized.

Triangle SRT and triangle TRQ can be compared using the image. Since both triangles have equal sides and right angles (T), they are both triangles (RT)

Using Pythagoras theorem,  

RQ² = TQ² + TR²

20² = TR² + 16²

TR = 12

SR/RQ = TR/TQ

SR / 20 = 12 / 16

SR = 15 units

Hence the length of SR will be 15 units.

Learn more about Pythagoras theorem, by the following link

https://brainly.com/question/231802

#SPJ4

The figure below is a net for a right rectangular prism. Its surface area is 272 m2 andthe area of some of the faces are filled in below. Find the area of the missing faces,and the missing dimension.

The figure below is a net for a right rectangular prism. Its surface area is 272 m2 andthe area of some

Answers

the surface area of a prism is the sum of the areas of all its sides. The surface area is given: 272 m².

We also have the area of 4 of the the sides. The area of the missing ones is the same, since it is a right rectangular prism. So we can write:

\(\begin{gathered} 16+16+24+24+A+A=272 \\ 80+2A=272 \\ 2A=272-80 \\ 2A=192 \\ A=96 \end{gathered}\)

So the area of the missing faces is 96 m².

Since it is a rectangle of area 96 m² and one side of 8 m, we can find the length of the missing side, "x", by noticing that the area is calculated by the multiplication of the sides:

\(\begin{gathered} A=8\cdot x=96 \\ x=\frac{96}{8} \\ x=12 \end{gathered}\)

So, the missing dimension is 12 m.

The triangular prism below has a base area of 31 units^2

and a volume of 310 units^3

Find its height.

Answers

Given:\( A_{B} = 31 \: {units}^{2} \)\(V = 310 \: {units}^{2} \)To find:

The height of the given triangular prism.

Solution:

\(h = \frac{V}{ A_{B}}\)

\(h = \frac{310}{31} \)

\(\large\boxed{\sf{h=10 \: units}}\)

Therefore, the height of the given triangular prism is 10 units.

h= 310/31

h= 10 units

hope this helps

please help its due at 11:59 and i´m struggling!!!!

please help its due at 11:59 and im struggling!!!!

Answers

Answer:

hold on might have to ask my teacher

Step-by-step explanation:

Select the correct answer.

Colton is painting a set of figurines a solid color. It takes him 15 minutes and 5 milliliters of paint to finish a small figurine. It takes him 30 minutes and 8 milliliters of paint to complete a large figurine. Colton plans to paint for at least 360 minutes, and he can use a maximum of 100 milliliters of paint.

This graph and system of inequalities represent this situation, where x represents the number of completed small figurines and y represents the number of completed large figurines.

15x + 30 ≥ 360
5x + 8y ≤ 100

A line intercepts the x and y-axis at 20 and minus 11.25 units. Another line intercepts the y-axis at 11 units. Both intersect at (4, 10) with an orange region on the right side, pink on the upper and white on the lower, and blue on the left.

Which solution is valid within the context of the situation?

A.
(4,10)
B.
(-2,13)
C.
(1,11.75)
D.
(6,9)

Answers

The x and y have to be non-negatve integers.

We have given that,

Colton is painting a set of figurines in a solid color. It takes him 15 minutes and 5 milliliters of paint to finish a small figurine.

What is the intersection?

The intersection of a line and a line can be the empty set, a point, or another line. Distinguishing these cases and finding the intersection have been used, for example, in computer graphics, motion planning, and collision detection.

It takes him 30 minutes and 8 milliliters of paint to complete a large figurine. Colton plans to paint for at least 360 minutes, and he can use a maximum of 100 milliliters of paint.

The solution set is the purple region. The intersection lies at (4,10)

The region is towards the left of x=4 so it can't be D

x and y have to be non-negatve integers. So it can't be B or C.

To learn more about the intersection visit:

https://brainly.com/question/1214333

#SPJ1

the graph of f(x)=1/x is horizontally stretched by a factor of 2, then shifted to the left 1 unit and down 8 units.

Answers

The point (2, 150) will move to the point (2, - 7/4) after the transformation of the function.

The given function is f(x) = 1/x.

We need to horizontally stretch this function by a factor of 2, shift it to the left by 1 unit and down 8 units.

The general equation for the horizontally stretched function is g(x) = f(ax) / b, where a is the factor of horizontal stretch and b is the vertical shift.

Thus, the equation for the given function after stretching and shifting is:g(x) = (1 / 2x + 1) - 8g(x) = (1 / 2x) - (15 / 2)

Let's verify this equation using x = 1. When x = 1,f(1) = 1/1 = 1g(1) = (1 / 2(1)) - (15 / 2) = - 7/2

Thus, (1, 1) on f(x) maps to (1, - 7/2) on g(x). So, the point (2, 150) on f(x) will map to: g(2) = (1 / 2(2)) - (15 / 2) = - 7/4

Thus, the point (2, 150) on f(x) will map to (2, - 7/4) on g(x).

Therefore, the point (2, 150) will move to the point (2, - 7/4) after the transformation of the function.

Learn more about horizontally stretched function here https://brainly.com/question/29185378

#SPJ11

Help me please i need it for a grade in my math class so i dont fail

Help me please i need it for a grade in my math class so i dont fail

Answers

Answer: Yes.

Step-by-step explanation:

Yes, is the answer, it’s just greater.

Which of the following is a characteristic of a binomial problem a. There are n identical trials, and all trials are independent has two possible outcomes which are traditionally labeled "failure" and "success" and the probability of success p is the same on each trial. c. We are interested in x, the number of successes observed during the n trials. d. All of these are characteristics of a binomial experiment. e. None of these

Answers

all the characteristics mentioned in options a, b, and c are true for a binomial experiment. Thus, the correct answer is d. All of these are characteristics of a binomial experiment.

The correct answer is d. All of these are characteristics of a binomial experiment.

A binomial experiment is characterized by the following:

a. There are n identical trials, and all trials are independent.

b. Each trial has two possible outcomes, traditionally labeled "failure" and "success."

c. The probability of success, denoted as p, is the same on each trial.

d. We are interested in the number of successes observed during the n trials.

To know more about binomial visit:

brainly.com/question/30339327

#SPJ11

Carlos has 38 apples. He puts 8 apples into each bag if he fills as many bags as possible, how many apples are left

Answers

Answer:

6

Step-by-step explanation:

What you need to do is 38 ÷ 8. The answer would be 4 with a remainder of 6, so there are six apples left

Please show all work pleaseee

Please show all work pleaseee

Answers

The horizontal asymptote is y = 2, and the vertical asymptotes are x = -2 and x = -3.

What is asymptote?

An asymptote is a line that a curve approaches but never touches as it extends to infinity. In other words, it is a line that a function approaches as the input values become very large or very small. Asymptotes can be vertical, horizontal, or oblique. Vertical asymptotes occur where the denominator of a function becomes zero and the numerator does not. Horizontal asymptotes occur where the degree of the numerator is less than or equal to the degree of the denominator. Oblique asymptotes occur where the degree of the

To find the horizontal asymptote, we look at the highest power of x in the numerator and denominator. In this case, both the numerator and denominator have the same highest power of x, which is x². Therefore, the horizontal asymptote is given by the ratio of the leading coefficients of the numerator and denominator, which is 2/1 = 2.

To find the vertical asymptotes, we set the denominator equal to zero and solve for x:

x² + 5x + 6 = 0

This quadratic equation factors as:

(x + 2)(x + 3) = 0

So the vertical asymptotes occur at x = -2 and x = -3.

Therefore, the horizontal asymptote is y = 2, and the vertical asymptotes are x = -2 and x = -3.

To know more about asymptotes visit:-

https://brainly.com/question/4138300

#SPJ1

Given y = 2 - 6 if x = 2, what is the value of y

Answers

Answer:

im gonna assume you mean y=2x-6, if so the answer is -2 (multiply 2*2 then subtract 6)

if you really did mean y=2-6, then you would just subtract 6 from 2 and your answer would be -4

1 4/5 = 2/5 + r HELPPPPPPPPPPPPPPPPPPPPP

































Answers

Answer:

r=7/5

Step-by-step explanation:

Help me with this worksheet

Help me with this worksheet

Answers

Answer:

A.)

Rise = 2

Run = 5

m = 2/5

B.)

Rise = 2

Run = - 4

m = - 1/2

C.)

Rise = 3

Run = 1

m = 3

Step-by-step explanation:

Rise = y2 - y1

Run = x2 - x1

Slope, m = Rise / Run

A.) (0,0) ; (5 2)

x1 = 0 ; y1 = 0

x2 = 5 ; y2 = 2

Rise = 2 - 0 = 2

Run = 5 - 0 = 5

m = 2/5

B.) (1, 2) ; (-3, 4)

x1 = 1 ; y1 = 2

x2 = - 3 ; y2 = 4

Rise = 4 - 2 = 2

Run = - 3 - 1 = - 4

m = 2/-4 = - 1/2

C.) (5,2) ; (6,5)

x1 = 5 ; y1 = 2

x2 = 6 ; y2 = 5

Rise = 5 - 2 = 3

Run = 6 - 5 = 1

m = 3/1 = 3

Can someone help me with this math homework please!

Can someone help me with this math homework please!

Answers

Answer:

1: (C)

2: (C)

3: (D)

4: (A)

5: (D)

Step-by-step explanation:

1: "Which could be the entire interval over which the function, f(x), is negative?"

When f(x) is negative, that means the values under the f(x) column is negative. As you can see, -16 & -8 are the only times when f(x) is negative. To find the interval, we are going to use x-values. Notice how as x continues to decrease, f(x) also decreases. So the answer is (-infinity, -6).

2: "Which equation represents the graphed function?"

Looking at the graph, we see that the y-intercept is (0, -2). However, all the answer choices have the correct y-intercept, so now we must focus on getting the correct slope. The slope is positive, so the answer is either (A) or (C). To find the correct answer, use the rise/run method from (0, -2) to (4, -1). You rise 1 and run 4, so the slope is 1/4. The answer is y = 1/4x - 2.

3: "If f(1) = 10, what is f(3)?"

I honestly don't know how to do this one. I looked it up on Brainly and some other people said the answer is 30. Credits to dragonheartedking on Brainly.

4: "Which table represents a linear function?"

Table A represents a linear function because each time x increases by 1, y increases by the same amount of 4 each time. It doesn't fluctuate like the rest of the answer choices.

5: "How many units below the y-intercept of g(x) is the y-intercept of f(x)?"

The y-intercept is the point where the function intersects with the y-axis. We start from (0, 2) and count the units as we reach (0, -1). The answer is 3 units.

Hope this helps (●'◡'●)

Answer:

Step-by-step explanation:

Can someone help me with this math homework please!
Can someone help me with this math homework please!

A delivery truck is transporting boxes of 266 large and small. The combined weight of a large box and a small box is 80 pounds. The truck is transporting 50 large boxes and 55 small boxes. If the truck is curing a total of 4150 pounds in boxes how much does each type of box weigh

Answers

Answer:

Step-by-step explanation:

FINSH THAT THEN YOU CAN START ALL THE OTHER ONES

An equation of a line through (-12, -12) which is parallel to the line y = 3 x + 2 has slope:

Answers

Answer:

3. Parallel lines have the same slope but different y-intercepts, so they never intercept each other.

Step-by-step explanation:

 An equation of a line through (-12, -12) which is parallel to the line y = 3 x + 2 has slope:

Type the correct answer in each box. Use numerals instead of words. The function f(x)=x^1/2 is transformed tp get function w. w(x)=-(3x)^1/2-4 What are the domain and the range of function w?​

Answers

The domain is; x ≥ 0

The range is; w(x) ≤ 4

How to find the domain and range of a function?

The transformed function is given as:

w(x) = -\((3x^{\frac{1}{2} })\)

Rewriting the function, by applying the law of fractional exponents:

w(x) = -(√3)x - 4

The domain of a function is the set of all input values that make the function defined.

The function is undefined when the value of x under the root sign is less than zero because the square root of a negative number is complex.

Hence, the domain exists when x has a value greater than or equal to 0.

Therefore, the domain is; x ≥ 0

The range of a function is the set of all output values that makes the function defined.

Hence, the range exists when y is lesser than or equal to minus 4 because a value of y greater than -4, makes the function and domain undefined.

Therefore, the range is;

w(x) ≤ 4

Read more about Domain and range at: https://brainly.com/question/2264373

#SPJ1

Bubba invests $103 at 5% interest and leaves it alone for 9 years. How much money should be in his account at the end of that time?

Answers

Bubba should have approximately $156.14 in his account at the end of 9 years if he invests $103 at a 5% interest rate.

To calculate the final amount in Bubba's account, we can use the formula for compound interest: A = P(1 + r/n)^(nt), where A is the final amount, P is the principal (initial investment), r is the interest rate (as a decimal), n is the number of times interest is compounded per year, and t is the number of years.

In this case, Bubba invests $103 at a 5% interest rate. The interest is compounded once per year (n = 1), and he leaves the money untouched for 9 years (t = 9). Plugging these values into the formula, we have A = 103(1 + 0.05/1)^(1*9). Simplifying the equation, we get A = 103(1.05)^9. Calculating the expression within the parentheses, we have A = 103(1.551328). Multiplying these values together, we find that A is approximately $156.14. Therefore, Bubba should have approximately $156.14 in his account at the end of 9 years if he invests $103 at a 5% interest rate.

Learn more about equation here:

https://brainly.com/question/29538993

#SPJ11

(6.6 × 10⁰) + (7.8 × 10²)​

Answers

Answer:

786.6

Step-by-step explanation:

Anything to the ^0 is 1 so its 1 x 6.6 + 100 x 7.8

6.6 + 780

786.6

Answer:

786.6

Step-by-step explanation:

Problem:

(6.6 × 10⁰) + (7.8 × 10²)​

Step 1 - Parenthesis:

(6.6 × 10⁰) + (7.8 × 10²)​

Step 2 - Exponents(Left to Right):

(6.6 × 10^0) + (7.8 × 10^2)​ = (6.6 × 1) + (7.8 × 100)

Step 3 - Multiply(Left to Right):

(6.6 × 1) + (7.8 × 100) = 6.6 + 780

Step 4 - Add(Left to Right)

6.6 + 780 = 786.6

Step 5 - Answer:

786.6

Remember:

Parenthesis

Exponents(Left to Right)

Multiplication(Left to Right)

Division(Left to Right)

Addition(Left to Right)

Subtraction(Left to Right)

Marcus found a website where gold jerseys cost $150 and blue jerseys cost $50. He plans on spending $300. He is buying 4 jerseys. Use x to represent gold jerseys and y to represent blue jerseys. Write the system of linear equations to represent this situation

Answers

Answer:

150x+50y=300

150(1)+50(3)=300

x+ y=4

Step-by-step explanation:

He is wanting spend 300 he needs to know how many shirts should be sold for each to add to that total. He wants 4 shirts so he needs 3 of the 50 dollars and 1 of the shirts that cost 150.

Find sin (x - y) if sin x = 3/5 and cos y = 5/13. Assume both triangles are in quadrant 1.

Answers

The value of sin (x - y) of the triangles is -33/65

How to find the value of sin (x - y) of the triangle?

Trigonometry is the branch of mathematics that deals with the relationship between ratios of the sides of a right-angled triangle with its angles

Given: sin x = 3/5 and cos y = 5/13.  Both triangles are in quadrant 1

(Consider the image attached)

For triangle with angle x

adjacent = √(5²-3²)  = 4

cos x = 4/5 (adjacent/hypotenuse)

For triangle with angle y

opposite = √(13²-5²)  = 12

sin y = 12/13 (opposite/hypotenuse)

Using the trigonometric identity:

sin(x-y) = sinxcosy - sinycosx

sin(x-y) = (3/5)×(5/13) - (12/13)×(4/5)

sin(x-y) = 3/13 - 48/65

sin(x-y) = -33/65

Learn more about trigonometry on:

brainly.com/question/29354606

#SPJ1

Find sin (x - y) if sin x = 3/5 and cos y = 5/13. Assume both triangles are in quadrant 1.

you are going to create a caramel cheese popcorn mixture. one cup of caramel popcorn contains 183 calories, 5.4 grams fat, 22.5 grams sugar, and 87 mg of sodium. one cup of cheese popcorn contains 58 calories, 3.7 grams fat, 0.1 grams sugar, and 98 mg sodium. if you create a mixture that has two times as much cheese popcorn as caramel popcorn and contains a total of 254 calories, how many cups of each item would be in your mixture. be sure to clearly define the variables used, define the two equations, and show and explain all work.

Answers

The mixture would contain approximately 0.849 cups of caramel popcorn and 1.698 cups of cheese popcorn.

Let's define the variables:

Let x be the number of cups of caramel popcorn in the mixture

Let y be the number of cups of cheese popcorn in the mixture

We are given that the mixture has two times as much cheese popcorn as caramel popcorn, so y = 2x.

We are also given that the total number of calories in the mixture is 254. To find an equation that relates x and y, we can use the calorie information for each type of popcorn:

Calories from caramel popcorn = 183x

Calories from cheese popcorn = 58y = 58(2x) = 116x

Total calories in the mixture = 183x + 116x = 299x

Setting the total calories equal to 254 and solving for x:

299x = 254

x = 0.849

So we would need 0.849 cups of caramel popcorn in the mixture.

To find the number of cups of cheese popcorn, we can use the equation y = 2x:

y = 2(0.849) = 1.698

So we would need 1.698 cups of cheese popcorn in the mixture.

Therefore, the mixture would contain approximately 0.849 cups of caramel popcorn and 1.698 cups of cheese popcorn.

To learn more about mixture

https://brainly.com/question/13461506

#SPJ11

HELPPPP ME NOW PLS LLS

HELPPPP ME NOW PLS LLS

Answers

Answer:

Angle one is 107 degrees and angle 2 is 83 degrees

Step-by-step explanation:

A spherical hot air balloon inflates at a rate of 101 ft3/min. At what rate is the radius changing when the surface area is 20.2 ft2 ? [Note: V = 4/3r3, SA = 4 r2]

Answers

If a spherical hot air balloon inflates at a rate of 101 ft³/min.  The rate  that the radius is changing when the surface area is 20.2 ft²  is 0.

What is the rate of change?

Using the volume of a spherical balloon formula

V = (4/3)πr³

Take the derivative of both sides

dV/dt = 4πr² (dr/dt)

Substituting

20.2 = 4πr²

Differentiate both sides

d/dt (20.2) = d/dt (4πr²)

0 = 8πr(dr/dt)

Solve for dr/dt:

dr/dt = 0 / (8πr)

dr/dt = 0

Therefore the rate of change of the radius (dr/dt) is 0.

Learn more about rate of change here:https://brainly.com/question/8728504

#SPJ1

An airship flies 150km with the wind and then turns around and flies back, taking 6 hours and 15 minutes for the round trip. Find the speed of the wind if the speed of the airship in calm weather is 50 km/hr.

Answers

The speed of the wind is 10km/hr.

What is the speed?

A scalar quantity, speed is defined as the size of the change in an object's location over time or the size of the change in an object's position per unit of time.

Here, we have

Given: An airship flies 150km with the wind and then turns around and flies back, taking 6 hours and 15 minutes for the round trip.

We have to find the speed of the wind if the speed of the airship in calm weather is 50 km/hr.

150 = (50-c)(6.25-t)

6.25-t = 150/(50-c)

(6.25×50 - 6.25c -150)/(50-c) = t

t = (162.5 - 6.25c)/(50-c).....(1)

150=(50+c)t  

t = 150/(50+c)

Now, we put the value of t in equation (1) and we get

150/(50+c) = (162.5 - 6.25c)/(50-c)

150 = (50+c) (162.5 - 6.25c)/(50-c)

150 = (50+c)(162.5 - 6.25c)/(50-c)

150 = (8125 - 312.5c +162.5c - 6.25c²)/(50-c)

7500 - 150c = 8125 - 312.5c + 162.5c - 6.25c²

7500 - 150c = 8125 - 150c  - 6.25c²

7500 = 8125 - 6.25c²

8125 - 6.25c² - 7500 = 0

6.25c² - 625 = 0

c² = 100

c = 10

Hence, the speed of the wind is 10km/hr.

To learn more about the speed the given link

https://brainly.com/question/14719933

#SPJ1

I NEED HELP ON THIS ASAP!!!!

I NEED HELP ON THIS ASAP!!!!

Answers

Answer:

Step-by-step explanation:

2 would have a greater b value because its x.  Also the other answer is 2.

11-1 Skills Practice. Areas of Parallelograms and Triangles. Find the perimeter and area of each parallelogram or triangle.

Answers

The area of each parallelogram or triangle is 24 cm²,22.5 cm², 98 ft²,48 cm², 90 m², and  30 in² respectively.

In this skills practice problem, we are asked to find the perimeter and area of each parallelogram or triangle, based on their given dimensions. Let's start by defining the formulas for calculating the perimeter and area of each shape:

Perimeter of a parallelogram = 2 x (length + width)

Area of a parallelogram = base x height

Perimeter of a triangle = sum of the lengths of its sides

Area of a triangle = 1/2 x base x height

Now, let's apply these formulas to each shape:

Parallelogram with length 6 cm and width 4 cm:

Perimeter = 2 x (6 + 4) = 20 cm

Area = 6 x 4 = 24 cm²

Triangle with base 9 cm and height 5 cm:

Perimeter = 9 + 8 + 7 = 24 cm

Area = 1/2 x 9 x 5 = 22.5 cm²

Parallelogram with length 14 ft and width 7 ft:

Perimeter = 2 x (14 + 7) = 42 ft

Area = 14 x 7 = 98 ft²

Triangle with base 12 cm and height 8 cm:

Perimeter = 12 + 8 + 10 = 30 cm

Area = 1/2 x 12 x 8 = 48 cm²

Parallelogram with length 18 m and width 5 m:

Perimeter = 2 x (18 + 5) = 46 m

Area = 18 x 5 = 90 m²

For more questions like Triangle click the link below:

https://brainly.com/question/2773823

#SPJ11Triangle with base 6 in and height 10 in:

Perimeter = 6 + 8 + 10 = 24 in

Area = 1/2 x 6 x 10 = 30 in²

Therefore, we have calculated the perimeter and area of each given parallelogram or triangle.

For more questions like Triangle click the link below:

https://brainly.com/question/2773823

#SPJ11

One rabbit eats 8 carrots every day.

How many carrots does a rabbit eat in 7 days?

Answers

Answer:

56 carrots

Step-by-step explanation:

Because 7 x 8 is 56

Guys can you please help. I dont understand. Thank you. :))))

Lines AB and CD intersect at E. If the measure of angle AEC=5x-20 and the measure of angle BED=x+50, find, in degrees, the measure of angle CEB.

Answers

Answer: 112.5

Step-by-step explanation: When line AB and CD intersect at point E, angle AEC equals BED so you set them equal to each other and find what x is. 5x -20 = x + 50, solving for x, which gives you 17.5. Finding x will tell you what AEC and BED by plugging it in which is 67.5. Angle BED and BEC are supplementary angles which adds up to 180 degrees. So to find angle CEB, subtract 67.5 from 180 and you get 112.5 degrees.

an airplane has crashed on a deserted island off the coast of fiji. the survivors are forced to learn new behaviors in order to adapt to the situation and each other.

Answers

In a case whereby the  survivors are forced to learn new behaviors in order to adapt to the situation and each other. This is an example of Emergent norm theory.

What is Emergent norm?

According to the emerging norm theory, groups of people congregate when a crisis causes them to reassess their preconceived notions of acceptable behavior and come up with new ones.

When a crowd gathers, neither a leader nor any specific norm for crowd conduct exist. Emerging conventions emerged on their own, such as the employment of umbrellas as a symbol of protest and as a defense against police pepper spray. To organize protests, new communication tools including encrypted messaging applications were created.

Learn more about behaviors   at:

https://brainly.com/question/1741474

#SPJ4

complete question;

An airplane has crashed on a deserted island off the coast of Fiji. The survivors are forced to learn new behaviors in order to adapt to the situation and each other. This is an example of which theory?

Other Questions
1. analyze the three friends, luong, bien, and quan. what happens to them and why? how does the fate of these relationships tie into the novel's central theme? A Man buys two mobiles for Rs. 2,000 each. He sells one ofthem at 10% profit and other at 5% loss, what percent ofprofit or loss is there in the total transaction? In 1928 Kiyotsugu Hirayama grouped some asteroids into families. What is similar for the asteroids of a Hirayama family? A _____ is the basic structural and functional unit of the body.A. TissueB. OrganC. CellD. Organ system How long (in ns) does it take light to travel 0.800m in vaccum?Express your answer in the appropriate units Write the verbs. "This is how those friends of the devil ... opened the door of hellon their own farm." Is sprint planning an event? Which property is not used to simplify the following expression?(x+2)-5-7 = 5(x + 2) -7== (5x + 10) 7= 5x + (10 7=5x+3O commutative property of additionO commutative property of multiplicationassociative property of additionOO distributive property Why do cell plates form before the cells separate in plant cells? Select an answer and submit. For keyboard navigation, use the up/down arro a Plants cells have a mucus membrane b Plant cells have a cell wall c Plant cells have a plasma membrane d Plant cells have chloroplasts Calculate the FCF for Allied Foods Products if its total depreciation for 2019 was $100 million and its Balance Sheet ending December 2019 is as follows: (a,b,c or d)a. $71.50 millionb. -$71.50 millionc. $28.5 milliond. -$308.5 million Which of the following is the correct statement? a.The local variable can be accessed by any of the other methods of the same class b.The method's opening and closing braces define the scope of the local variable c.The local variable declared in a method has scope limited to that method d.If the local variable has the same name as the field name, the name will refer to the field variable What is the length of the unknown side of the right triangle? (1 point)A right triangle with hypotenuse x and legs 21 and 20A)21B)29C)400D)441 What is a smaller loop statement that can appear on the same line of code?an infinite statementa finite statementa repeat statementa single statement when ideo was asked to redesign the los angeles voting system, the key to success was to use empathy to understand the subtleties of the act of voting. Isaac has a total of 90 pennies, nickels, and quarters. He has 3 1/2 times as many quarters as nickels and 1/2 as many pennies as nickels. How many of each coin does he have? Which number completes the table for y = x2 ?x y0 04 16-3 __A. 6B. -6C. 9D. -9 What are the requirements for fine coating in electroplating method ? How have indigenous tribes in and around washington invested in the state and their own communities? be sure to include specific examples. The normal price of an item is H dollars. On a particular date, the store offers to take $30 off the price, then apply a 20% discount. Which expression finds the new price? Email invitation to other members of the committee